国产资源中文字幕,欧美最新大尺度电影未删减版下载,中文字幕视频三区,乱色视频中文字幕,色戒在线观看 完整版,九九色九九,玩偶传说未删减在线看完整版电影

軟題庫(kù) 移動(dòng)APP 掃碼下載APP 隨時(shí)隨地移動(dòng)學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Together with your team, you applied three-point estimation on a critical path which consists of two activities. The following duration uncertainties are all calculated assuming a ±3 sigma confidence interval. The duration uncertainty-defined as pessimistic minus estimate-of the first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths. What is the duration uncertainty of the entire path ?
A、21 days.
B、 30 days.
C、 42 days.
D、 No statements is possible from the information given.


相關(guān)試題

推薦文章