A specific, well-defined deliverables is being developed by a company facility located in a country. Management decided to sell this portion to different organization.The project manager is left with the task of replacing the capacity offered by that facility to the deliverables. If according to the budget and risk will be retained in the lower levels, what should the project manager do ?
A、Obtain the project resources to join the project to develop the deliverables.
B、Sign a contract with an external company to develop the deliverables.
C、Employ the contractor on a time and material basis to complete the deliverable.
D、Develop the deliverables and train the project’s resource currently allocated to other tasks.