A customer initiates a new strategic project, Which must be completed by the end of the year. The project is critical to the strategic success of the customer. An idea about the scope, budget, and timeline has already been discussed.What else should be included in the project charter?
A、Approved budget, named resources, and fixed-end date
B、Quantified risks, limits and exclusions, and revised milestone dates
C、High-level requirements, high-level risks, and identified scope
D、Project plan, scope plan, and resource plan