試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(6)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Project A is being administered using a matrix form of organization. The project manager reports to a senior vice president who provides visible support to the project. In this scenario, which of the following statements best describes the relative power of the project manager?
A、The project manager will probably not be challenged by project stakeholders
B、In this strong matrix, the balance of power is shifted to the functional line managers
C、In this tight matrix, the balance of power is shifted to the project manager.
D、In this tight matrix, the balance of power is shifted to the project manager.