試卷名稱 2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(7)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語模擬題(7)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A project manager gets a call from a team member notifying the project manager that there is a variance between the speed of a system on the project and the desired or planned speed. The project manager is surprised because that performance measurement was not identified in planning. If the project manager then evaluates whether the variance warrants a response, the project manager is in what project management process?
A、Initiating
B、Executing
C、Monitoring and controlling
D、Closing